Construction Permits Reforms

Government of the Punjab is committed to introducing reforms which will improve the business environment of the province. Following are the reforms which have been introduced:

Construction Reforms

2019
Nov 16

Step 1

Step 1

Automated building permit issuance system.

Oct 26

Step 2

Step 2

LDA has specified the time limit (30 days) for approval of building plans. If the plans are not sanctioned within 30 days, the owner can start construction.

Sep 12

Step 3

Step 3

Completion certificate fee for commercial building has been fixed at Rs. 10,000.

Aug 09

Step 4

Step 4

LDA has notified only 1 inspection during construction of warehouse by amending building by-laws.

Jul 07

Step 5

Step 5

As per Lahore Development Authority’s (LDA) Amended Building & Zoning Regulations 2019, an NOC is no longer required for obtaining building permit for non- hazardous warehouse.

Jun 19

Step 6

Step 6

LDA has automated the process of paying building permit and completion fee therefore these dues can be paid via debit/credit card and ATM.

May 23

Step 7

Step 7

As per LDA’s amended Building & Zoning Regulations 2019, application for water & sewerage connection can be submitted along with building permit application.

Apr 23

Step 8

Step 8

Cost for water & Sewerage Connection is PKR 1,750.

Mar 16

Step 9

Step 9

Amendments in building by laws for outsourcing of inspections.

Jan 17

Step 10

Step 10

Joint inspection of water & sewerage connection by WASA.